33-40 Charterhouse
Square.
The Vision
Located in the heart of the City of London’s conservation area, this two-stage project for Cognita Schools involved the partial refurbishment of an occupied building and the conversion of an adjacent derelict structure.
The works were split into two distinct parts: Buildings A&B (the existing school) and Building C (a derelict property). The objective was to expand the school into previously vacant office floors and the neighbouring building, requiring significant structural alterations and careful logistical management.


Value Engineering & Partnership
"We worked closely with the client team during the second stage to develop the design, arriving at a contract sum based upon robust market prices. When the initial sum exceeded the budget, we co-operated to value engineer packages, maintaining expectations without compromising quality."

Project Partners
- ClientCognita Schools Ltd
- ArchitectEllis Williams Architects
- Contract AdminCube Management LLP
- Structural EngineerAxiom Structures
Designed for Learning
Formerly derelict areas were turned into bright, practical teaching spaces for pupils and staff.















Navigating Complexity
Delivering education facilities in the heart of London required careful planning, close coordination and a strong focus on safety.
Barbican Tube Proximity
The rear of the buildings backed directly onto Barbican tube station. This required nightly erection and dismantling of access equipment outside of normal working hours to ensure public safety and TFL compliance.
Live School Environment
Works were carried out during full school occupation. We implemented strict cordons, security monitoring, and partnered with Estates Management to schedule noisy works around teaching priorities.
Structural Variations
In Building C, existing steelwork was found to be inconsistent with records. We proactively designed temporary support solutions and collaborated with the SE to resolve design changes swiftly.
Built with Confidence
Despite the significant design changes in Building C which led to a 15-week Extension of Time, the project was completed amicably with extremely positive feedback from the school.
Successful delivery of a sensitive, multi-stage education refurbishment in the City of London.